Farmhouse Update!


It's been awhile since I've written an update on our farmhouse and it feels like things are moving so quickly now! Here's a glimpse into what we've been up to:


December 17: The front gable was put on the house

December 18: The doors and the windows were installed

December 24: The roof was installed, interior framing was complete, the base for the front porch was built and the stairs to the basement were built

January 1: The fireplace was installed and the electrician began installing electrical boxes throughout the house

January 7: The subfloors were prepped

January 19: Guest tub and master tub was moved into their locations

January 25: Vents were cut into the floors and the rest of the HVAC was installed. The basement floors and the garage floors were poured

February 1: Siding install began! Plus, the rooms in the basement were framed and plumbing was run to the basement bathroom

February 5: Siding was finished, the porch ceiling was installed and all light boxes were installed


I'm so excited to continue to show you updates! You can follow along on Instagram @farmhouseinthefield to see more pictures as the progress continues.